By Darren Lewis — paving contractor, 23 years in the trade, and founder of SiteSnap Pro.
A snag list is a record of all the defects and unfinished work found when a building project — or a stage of it — is inspected before handover. Each item (“snag”) is written down with its location, a description of what's wrong, the trade responsible for fixing it, and its status. Once every snag is closed, the work is accepted.
The word “snag” just means a minor fault: a door that catches, mastic that's missed, paving blocks not fully bedded, paint runs, a cracked tile. Individually small; collectively the difference between a job that's finished and one that isn't.
If you want to get straight to it, there's a free snag list template here — Excel and printable PDF.
Broadly, yes. “Snag list” (or “snagging list”) is the UK and Irish term. In the US the same document is a “punch list”. Formal UK contracts (JCT, NEC) tend to say “defects list” or “schedule of defects”, and a defect found after handover during the rectification period is treated differently from a snag found before it. More detail: punch list vs snag list.
Depends on the job. On small domestic work, usually the contractor themselves, sometimes with the client. On commercial projects, the main contractor snags their subcontractors' work first, then the architect, contract administrator or clerk of works carries out the formal inspection. The best-run jobs snag their own work before anyone else gets the chance to.
Most snagging arguments aren't about whether something was wrong — they're about when: was the paving damaged before or after handover? Was the fix done inside the agreed window? A written list can't answer that. A photo with a timestamp and location can. Keep photos attached to their snags, not loose in a camera roll, and most disputes never get started. (This is exactly what SiteSnap Pro does: photos tagged to client, site and plot as you take them, snags assigned to the person fixing them, and a PDF report at the end.)
Finding and fixing the minor defects and unfinished items on a building project before it's handed over — and keeping a record (the snag list) of what was found and when it was put right.
A room takes minutes; a house an hour or two; a multi-plot site is usually snagged plot by plot as each finishes. Closing the snags out depends on the trades involved.
In everyday use, nothing. In formal contracts, “defects” usually refers to faults appearing after practical completion, during the rectification period, while snags are caught before handover.
Not for a one-off small job — a template does fine. Software earns its keep when there are photos, multiple trades, or more than one person raising and closing snags.